Discover places near you!

Share your location to see hidden gems within walking distance.

New Central Wastewater Treatment Plant

The New Central Wastewater Treatment Plant (Mongolian: Төв цэвэрлэх байгууламж) is a wastewater treatment plant under construction in Songino Khairkhan District, Ulaanbaatar, Mongolia.

Location

1 explorer visited this place

History

The feasibility study to establish the plant was done in 2015. The construction of the plant was officiated on 2 February 2019 and constructed officially started on 28 February 2019 in a groundbreaking ceremony officiated by Prime Minister Ukhnaagiin Khürelsükh. On 31 March 2022, concrete started to be poured into the inner walls of the plant three reaction tanks. In July 2025, the plant received its first trial inflow of.

Architecture

The plant is constructed in a 17.7 hectares of land. There are 35 buildings being constructed at the plant site.

Technical specifications

Once completed, the plant will have a processing capacity of 250,000 m3 of wastewater per day.

Finance

The plant costs US$262.7 million which was financed by a loan provided by the Government of China to the Government of Mongolia.

See also

Environmental issues in Mongolia

Book your tour near New Central Wastewater Treatment Plant
Book Now
4.2
in partnership with GetYourGuide.com